Elm Street reconstruction in E. Longmeadow finishing up

Final paving scheduled for August 8th

elm street gas leak 1

EAST LONGMEADOW, Mass. (WWLP) – Some good news for drivers and residents in East Longmeadow. The Elm Street reconstruction project is in it’s final stages.

Elm Street was in the news twice in less than a week after accidental gas leaks.

DPW Superintendent Robert Peirent gave 22News an update on the project. Final paving is scheduled for the week of August 8th, but as of Wednesday July 30th, thru traffic will be allowed on Elm Street and Mapleshade Avenue.

Crews still need to grade the road and install new underground wiring for traffic signals.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s